Construction on the Dingwall Road water main replacement project is moving to the next stage. The City of Courtenay’s Transportation Manager Craig Perry says the next phase is to connect the new system to the existing one. Traffc will be reduced to a single-lane while the work is being done. The work schedule and intersections affected are as followed:

Tuesday November 22: 7:30 am – 5:00 pm at Dingwall & Northland and Dingwall & McIntyre

Wednesday November 23: 7:30 am – 5:00 pm at Dingwall & Western

Thursday November 24: 7:30 am – 5:00 pm at Dingwall & McLauchin

Perry says the next step is to finishing paving the road which should be done by the end of November.